Rock breaking is ongoing at the new gym site. This should be completed right after Thanksgiving. Crews have been putting piers in place for the building. Once rock breaking is complete, foundation should be poured and you will begin to see the building going up.
The new fieldhouse site is being prepared for the building. The sod has been removed. The irrigation system was saved to be used elsewhere in the future. The pre-fabricated building should arrive in early December. That will go up, then the additional work on the "bump out" in front of the building will be done. That is the area in front of the prefab building that will house restrooms and storage. Work will also need to be done around the parking lot. Building complete August 2027 with continued parking lot and landscaping work to continue.